A study of 403 US hyperscale data centers estimates that they consumed 82 terawatt-hours of electricity between May 2024 and April 2025. That equals about 1.8% of US demand and exceeds the annual electricity use of 148 individual countries, including Austria, Israel and Venezuela.

Researchers identified the facilities with satellite imagery, estimated demand from their electrical capacity and combined that with Environmental Protection Agency data on local power grids. They calculated 25.7 million metric tons of carbon dioxide emissions, comparable to Denmark’s annual footprint. About 54% of the electricity serving the sites likely came from gas and coal.

Location changed the result sharply. A kilowatt-hour used in coal-heavy Wyoming produced roughly seven times the carbon emissions of one used in hydropower-rich Oregon. The study covers hyperscale facilities, not only AI workloads, and relies on estimates because operators generally do not publish site-level consumption.

The calculation also excludes local air pollution from new gas infrastructure and on-site turbines. Researchers are building a public tracker for individual facilities, while a bipartisan bill in Congress could require national disclosure of data-center electricity use. More transparent site data would let communities judge power and climate costs before long-lived energy infrastructure is built to support a new project.